UPCOMING WORK

CBG Building Company is approaching a significant milestone as we top out the structure of the building in August 2025, with the bridge construction continuing through September 2025. Exterior framing and facade will continue through the end of 2025.

Dominion Energy (DEV) is expected to commence with managing their work associated with permanent power along N Lynn and 19th Street in July/August 2025, which is expected to take through the end of 2025 to complete.

Hover or click on a calendar item for details regarding any work activities that will have specific or atypical community impacts (i.e. road closures, night work, etc.). If no items are indicated, no specific community impacts are anticipated at this time.


LATEST PROGRESS

July 2025

The building structure continues to go vertical as the first twenty-five floors have been constructed and the exterior facade has commenced for the brick and Quest towers. The Level 26 bridge construction is to commence in July 2025.